2017 Bond Progress

2017 Bond Project Progress

PDF DocumentThe list of approved Bond Projects

Spring of 2019 Progress

  • Demolition for work at WWMS Auditorium to begin May 1.
  • New lights installed at WWT Stadium.
  • Demolition for new grandstands and concession building at WWT Stadium to begin May 21.
  • New doors and windows being installed at WWEC.
  • New HVAC Controls being installed in all buildings - this project will continue through the Fall.

Winter of 2019 Progress

  • Contracts awarded for work at WWMS Auditorium. Demolition and construction to begin May 2019.
  • Contracts awarded for work at the WWT Stadium. Demolition and construction to begin May 2019.
  • Contracts awarded for new secure entrances at Pinewood and Westwood.
  • Plans in progress for new secure entrance at WWMS.

Fall of 2018 Project Completion

  • Digital Signs installed at Briarwood, Westwood and WWMS
  • Partial Roof Replacement at Warren Woods Education Center
  • New dugouts at WWT for Softball and Baseball
  • New Fence at WWMS on the Baseball/Softball Field

January 2018 Progress

  • Meetings are occurring to select which projects will be bid out for the Summer of 2018
  • Technology designers and principals are meeting to map out building security needs
  • Playground designers and principals are meeting to map out playground changes
  • Pilot furniture has been ordered for demonstration at the elementary level