No. Project Start Finish
1 Briarwood Elementary
New Addition (7months) 20-Jun-05 24-Feb-06
Renovation (2months) 20-Jun-05 19-Aug-05
2 Pinewood Elementary
New Addition (7months) 19-Jun-06 31-Dec-06
Renovation (2months) 19-Jun-06 18-Aug-06
3 Westwood Elementary
New Addition (9 months) 19-Jun-06 28-Feb-07
Renovation (2months) 19-Jun-06 01-Sep-06
4 Warren Woods Middle School
Renovation (18 months) 31-Aug-06 31-Dec-07
5 Tower
New Addition (7 months) 20-Jun-05 21-Apr-06
Gym Renovation (2months) 20-Jun-05 19-Aug-05
Science/Band/Locker Rm Renov. 18-Jun-08 17-Aug-08
6 Enterprise High School
Renovation 18-Jun-07 17-Aug-07
7 Hawthorn Center
Renovation 19-Jun-06 01-Sep-06
10 Maintenance/Transportation Bldg
Renovation 18-Jun-07 27-Jul-07
All Project Timelines Are Subject To Revision