| No. | Project | Start | Finish | |
| 1 | Briarwood Elementary | |||
| New Addition (7months) | 20-Jun-05 | 24-Feb-06 | ||
| Renovation (2months) | 20-Jun-05 | 19-Aug-05 | ||
| 2 | Pinewood Elementary | |||
| New Addition (7months) | 19-Jun-06 | 31-Dec-06 | ||
| Renovation (2months) | 19-Jun-06 | 18-Aug-06 | ||
| 3 | Westwood Elementary | |||
| New Addition (9 months) | 19-Jun-06 | 28-Feb-07 | ||
| Renovation (2months) | 19-Jun-06 | 01-Sep-06 | ||
| 4 | Warren Woods Middle School | |||
| Renovation (18 months) | 31-Aug-06 | 31-Dec-07 | ||
| 5 | Tower | |||
| New Addition (7 months) | 20-Jun-05 | 21-Apr-06 | ||
| Gym Renovation (2months) | 20-Jun-05 | 19-Aug-05 | ||
| Science/Band/Locker Rm Renov. | 18-Jun-08 | 17-Aug-08 | ||
| 6 | Enterprise High School | |||
| Renovation | 18-Jun-07 | 17-Aug-07 | ||
| 7 | Hawthorn Center | |||
| Renovation | 19-Jun-06 | 01-Sep-06 | ||
| 10 | Maintenance/Transportation Bldg | |||
| Renovation | 18-Jun-07 | 27-Jul-07 | ||
| All Project Timelines Are Subject To Revision | ||||