The Instrumental Storage room is receiving new flooring. The music casework is on site and will begin to be set starting next week.
Warren Woods Tower High School- July 10, 2008
The locker room benches have been poured throughout the locker rooms.
Warren Woods Tower High School- July 10, 2008
The gym lights are being hung. Painting of the ceiling is scheduled to start next week.
Warren Woods Tower High School- July 10, 2008
Most of the toilet rooms have completed flooring. The painter has started painting walls which include an accent stripe.
Warren Woods Tower High School- July 10, 2008