Warren Woods Tower High School- June 14, 2007
The two new Lochivar Knight boilers have been installed in Tower’s pool equipment room.

Warren Woods Tower High School- June 14, 2007
Piping continues on the pool heat exchanger assembly.
Warren Woods Tower High School- June 14, 2007
The exhaust and intake piping has been completed from the pool boilers up thru a chase to the roof.
Warren Woods Tower High School- June 14, 2007
Tower’s main gym lighting retrofit is well underway. The old lights will be
removed early next week once the new lights are working. The new lights will
provide a much whiter light and will have three different light levels – two,
four or six bulbs can be turned on at each fixture.
Warren Woods Tower High School- June 14, 2007
Tower’s main boiler room piping continues. This photo shows the four new pumps
that will drive the chilled water system. The pumps in the foreground are 40
horsepower and the pumps in the background are 15 horsepower. The 40 HP pumps
will circulate the chilled water thru the building while the 15 HP pumps
circulate the chilled water thru the proposed electric rotary chiller.
Warren Woods Tower High School- June 14, 2007
The domestic water heater piping continues at Tower. The sunshine is coming
thru a large curb that was cut in the roof. The mechanical contractors are
lowering all of the equipment thru the curb using a crane.
©Warren Woods Public Schools 2007