New front entry walks are complete, and the mansard
roof over the Principal’s office is underway. The asphalt parking lot will be
topped later this week.

Briarwood Elementary - August 17, 2005
Classrooms are complete (typical classroom shown).

Briarwood Elementary - August 17, 2005

Briarwood Elementary - August 17, 2005
The main corridor is nearly finished.

Briarwood Elementary - August 17, 2005
The media center cmu walls are progressing. The large opening in the center of the photo is a window system that will divide the main corridor and the new computer lab.
The mason’s mobile scaffold system is in place and
ready to start constructing the west wall of the aux gym.

Briarwood Elementary - August 17, 2005
Sidewalks are being poured on the east side (back)
of the building.

Briarwood Elementary - August 17, 2005