Briarwood Elementary - August 3, 2005

Masonry complete at new staff lounge and storage room addition.  Steel bar joists have been installed and metal roof decking is starting to be installed.  

 


Briarwood Elementary - August 3, 2005

Masonry is underway for the new multi-purpose room.  This photo is taken at the southwest corner of the building looking north.


Briarwood Elementary - August 3, 2005

New TPC addition.  Slab has been poured and steel roof deck will be installed shortly.

 


Briarwood Elementary - August 3, 2005

New TPC addition from outside.  Mansard roofs will be reconnected.


 

 