The boiler room has received a fresh coat of paint and new epoxy flooring.


The split face is being laid at the Receiving area and on the south side at the POHI area. Inside the POHI/Receiving area, masonry walls continue to be built. Construction is scheduled to begin in the rest of the 700 wing over Christmas break when the remaining 11 classrooms are moved. Friday of last week, 12 classrooms were moved from various wings into the newly completed 500 wing.