Westwood Elementary School- January 24, 2007
The polyurethane flooring began Monday, 1/22/07, and will be complete by 1/26/07. There will be a 5 day curing period before any foot traffic is allowed on the floor.

Westwood Elementary School- January 24, 2007
The kitchen equipment is being set in place.

Westwood Elementary School- January 24, 2007
Millwork is being installed in the Workroom, to the right of the picture, and also in the sink alcove of the Media Center, to the left of the picture.
©Warren Woods Public Schools 2007