Here are this weeks progress photos for Warren Woods Middle School:

May 15, 2007
The ceiling tile has been installed down the corridor.

May 15, 2007
The flooring has begun to be installed in the corridor, starting at the south end of the corridor and working north.

May 15, 2007
The temporary partition wall has been removed in anticipation of installing the glass in the administration windows, painting the window frames and finishing the renovated wing.
The electrical overhead inspection passed today,
so we are in the process of dropping ceiling tiles in the classrooms and the corridors.
The fritz tile flooring is scheduled to be laid on Monday, 5/14/07,
and the corridor painting will be complete before hand.