Here are this weeks progress photos for Warren Woods Middle School:

May 9, 2007

The interior wood doors are being swung.

May 9, 2007

Toilet accessories are being installed in the D wing toilet rooms. This lav is located in the Administration area.

The electrical overhead inspection passed today, so we are in the process of dropping ceiling tiles in the classrooms and the corridors. The fritz tile flooring is scheduled to be laid on Monday, 5/14/07, and the corridor painting will be complete before hand.