March 28, 2007
Metal studs, rough electrical and wood blocking installed at the new Administration area in D-Wing (200).

March 28, 2007
Fire safing installed above masonry wall and under existing deck to achieve fire rating at the corridor in D-Wing (200).

March 28, 2007
Painting of existing and new CMU walls has started in the D-Wing (200) Class Rooms.

March 28, 2007
Building is completely demolished and backfill is almost complete.