Warren Woods-Tower High School- November 17, 2005
The walls and ceiling in the new aux gym have been painted – grey on top, white
on the bottom. The ductwork and light fixtures have been installed. The picture
shows iron workers installing steel to support the new basketball backstops,
which will be installed this week. The wood flooring is scheduled to begin next
week.

Warren Woods-Tower High School- November 17, 2005
The masons are building brick columns to enclose the steel at the new covered canopy/lobby area.

Warren Woods-Tower High School- November 17, 2005
This is the new storage room located just east of the expanded girl’s locker room. The walls and ceiling have been painted and flooring has been installed.

Warren Woods-Tower High School- November 17, 2005
The base for the new tile flooring is being installed in the concessions room. The room will be complete with a rolling shutter, refrigerator, hot dog grille and popcorn maker among other food service equipment.