Warren Woods-Tower High School- November 9, 2005
Last Wednesday, the steel was being set. This week, the steel is complete,
metal deck has been installed and and the electricians are running conduit under
the deck.

Warren Woods-Tower High School- November 9, 2005
The drywall ceiling have been installed and the entire room has been installed, and the entire room has been painted. The boy's toilet room is moving along at the same pace.

Warren Woods-Tower High School- November 9, 2005
The main corridor which separates the new building from the existing is receiving permanent light fixtures. The ceiling grid is up and perimeter ceiling tiles are being installed.

Warren Woods-Tower High School- November 9, 2005
The girl's locker room expansion has received its drywall ceilings and has light fixtures being installed. The concrete locker bases have been built, and are awaiting the metal lockers, scheduled to be installed mid December. The door and window shown on the left of the picture lead into an office.
©Warren Woods Public Schools 2005