Warren Woods-Tower High School- October 26, 2005

Site concrete is complete. Honey locust trees will be planted, one each, in the concrete box outs shown on the left side of the picture.
 


Warren Woods-Tower High School- October 26, 2005

This is a picture of the new women's toilet room. Rough plumbing is complete. The cabinet unit heater, show in the ceiling, and associated piping is being installed.



Warren Woods-Tower High School- October 26, 2005

Above ceiling ductwork, plumbing and electrical is being installed. The wall on the left side of the picture was the exterior wall of the existing gym and now becomes the west wall of the gym and now becomes the west wall of the new corridor separating the two gyms.

 


Warren Woods-Tower High School- October 26, 2005

Grading for the landscaping and asphalt paving has begun. Asphalt paving will begin the week of October 31, 2005.

 


Click to learn more about the Warren Woods District

Check out other Warren Woods schools

Check out employment opportunities in Warren Woods

Click to learn more about Warren Woods administration

Check out what's going on currently in Warren Wood's community.

Current Warren Woods alumni information.

©Warren Woods Public Schools 2004