Warren Woods-Tower High School- October 26, 2005
Site concrete is complete. Honey locust trees will be planted, one each, in the
concrete box outs shown on the left side of the picture.

Warren Woods-Tower High School- October 26, 2005
This is a picture of the new women's toilet room. Rough plumbing is complete. The cabinet unit heater, show in the ceiling, and associated piping is being installed.

Warren Woods-Tower High School- October 26, 2005
Above ceiling ductwork, plumbing and electrical is being installed. The wall on the left side of the picture was the exterior wall of the existing gym and now becomes the west wall of the gym and now becomes the west wall of the new corridor separating the two gyms.

Warren Woods-Tower High School- October 26, 2005
Grading for the landscaping and asphalt paving has begun. Asphalt paving will begin the week of October 31, 2005.