The new DTE power pole was set today, October 26! Power servicing the entire
building will come from this pole once the new transformer is set.

Briarwood Elementary - October 26, 2005

Briarwood Elementary - October 26, 2005
Interior of the new classroom. Electrician is shown installing conduit.

Briarwood Elementary - October 26, 2005
Plywood has been install for the mansard roof at the new classroom. Shingling of the mansard roof here and at the new TPC Room to follow shortly.

Briarwood Elementary - October 26, 2005
The new teachers lounge has been complete - and is in use - with the exception of the millwork, which will be installed with the new addition millwork